October is building season on many Kenyan farms. The long rains harvest is in, there is a little cash in hand, and the short rains are a reminder of every place where water pools, mud builds up and floors crack. So the jobs go on the list: a concrete base for the new water tank, a floor for the zero-grazing unit, a feed trough, a slab under the chaff cutter, footings for a goat house. Most of them are small enough that nobody orders ready-mix. A fundi turns up with a shovel, a few bags of cement, a heap of sand and a heap of ballast, and the concrete is mixed by hand on the spot.

Hand-mixed concrete can be excellent. It can also be weak, dusty and cracked within a year, using exactly the same cement. The difference is almost never the brand of cement. It is how the materials are measured, how much water goes in, how well the mix is turned and how the slab is treated for the first week of its life. Those are the four things this guide is about.

Below are the common mix ratios, a worked bag estimate, a step-by-step hand-mixing method, when to hire a mixer, and how to cure concrete in the short rains. Ratios here are the nominal mixes widely used on small Kenyan sites; for anything structural, such as a tank stand carrying many tonnes or a suspended slab, have the design checked by a qualified engineer.

Choose the Mix for the Job, Not Out of Habit

Concrete is cement, sand (fine aggregate), ballast (coarse aggregate) and water. The cement and water react to form a paste that glues the aggregates together. On small sites the mix is described as a ratio by volume of cement to sand to ballast. Three nominal mixes cover most farm work.

Nominal mix (cement : sand : ballast)Typical farm use
1 : 3 : 6Blinding under slabs, mass fill, bedding for paving where little strength is needed
1 : 2 : 4General work: floors of animal houses, paths, trough bases, small foundations, ground slabs
1 : 1.5 : 3Stronger work: tank bases, columns, lintels, slabs that carry machines or heavy loads, anything reinforced

The 1 : 2 : 4 mix is the workhorse, and it is what most fundis mean when they say "normal concrete". The richer 1 : 1.5 : 3 mix costs more cement per cubic metre but gives a denser, stronger concrete, which is worth it where the slab carries a full water tank or a posho mill that vibrates all day. A lean 1 : 3 : 6 mix is fine as a clean, level layer under a slab, but it should never be the slab itself.

Water is the hidden ratio. A mix can be measured perfectly by bucket and still be weak if too much water goes in. Extra water makes concrete easier to shovel, but every litre beyond what the cement needs leaves tiny voids as it dries out, and those voids are weakness, dust and cracks.

Measure by Bucket or Gauge Box, Never by Shovel

The most common fault on small sites is measuring by shovelfuls. Shovels of damp sand and dry ballast hold different volumes, and every labourer loads differently, so by evening the "1 : 2 : 4" has drifted into something else.

Use a standard container for every material. A 20-litre bucket works well for small batches; a simple timber gauge box, a bottomless box sized to hold an exact volume, is faster for larger pours. Fill each measure level, not heaped. Keep one bucket for cement only, so it stays dry and you are not adding wet sand clinging to its walls.

Damp sand bulks up, so a bucket of damp sand holds less actual sand than a bucket of dry sand. Keep sand covered and draw it from the same heap, in the same condition, for the whole pour.

Worked example: one bag of cement in a 1 : 2 : 4 mix One Bag of Cement, Measured in Buckets 1 : 2 : 4 mix, 50 kg bag, 20-litre buckets (worked example) about 35 L Cement about 1.75 buckets about 70 L Sand about 3.5 buckets about 140 L Ballast about 7 buckets
Worked example assuming loose cement weighs about 1,440 kg per cubic metre, so a 50 kg bag is roughly 35 litres. Bar heights are proportional to volume. Add water gradually; do not take a fixed number of buckets of water from this chart.

How Many Bags Do You Need?

Too little cement stops the pour halfway, leaving a weak joint between today's concrete and tomorrow's. Too much ties up cash in bags that harden in a damp store. A quick estimate avoids both.

Start with the wet volume: length times width times thickness, in metres. A slab 4 metres by 3 metres and 0.1 metres (100 mm) thick is 1.2 cubic metres. Dry materials shrink in volume when water is added and the fine particles fill the gaps between the coarse ones, so builders multiply the wet volume by about 1.5 to 1.55 to get the dry volume of materials. Here that is roughly 1.85 cubic metres of dry material.

In a 1 : 2 : 4 mix there are 7 parts in total, and cement is one of them. So cement is about 1.85 divided by 7, roughly 0.26 cubic metres. At about 1,440 kg per cubic metre, that is around 380 kg, or about 7.6 bags of 50 kg. Round up and buy 8, plus one spare bag for waste and for the inevitable extra corner. The same sum gives about 0.53 cubic metres of sand and 1.06 cubic metres of ballast. Use the steel measuring tape to measure the actual area rather than pacing it out; our guide to measuring and layout tools covers squaring a slab before you pour.

Hand-mixing allowance. Hand mixing is rarely as thorough as a mechanical mixer, and some site guidance adds around 10 percent more cement to hand-mixed batches to make up for it. On a small farm job that is usually one extra bag, and it is cheap insurance.

The Hand-Mixing Method, Step by Step

Good hand mixing follows a simple order: dry materials first, mixed until uniform, and only then water, added a little at a time. Every shortcut in this order shows up later as patches of weak concrete.

1. Prepare a mixing platform. Mix on a clean, hard, non-absorbent surface: an old slab, a steel sheet or a large timber board. Never mix on bare soil. Soil mixes into the concrete and weakens it, and dry ground sucks water out of the mix unevenly.

2. Spread the ballast, then the sand. Spread the measured ballast in a flat layer, then spread the sand on top of it.

3. Add the cement and dry-mix. Spread the cement over the sand and turn the whole heap over with a shovel from one side to the other, then back again. Keep turning until the colour is completely even, with no streaks of grey cement or brown sand. Three full turns is a common rule; more if the colour is still patchy.

4. Form a crater and add water gradually. Shape the heap into a ring with a hollow in the middle and pour in part of the water. Draw dry material from the sides into the water, turning carefully so water does not escape. Add the rest of the water in small amounts while turning.

5. Turn until uniform, then stop adding water. The mix is right when it is plastic and cohesive: it holds its shape when squeezed in a gloved hand without water running out, and a shovel cut through the heap leaves a clean face that does not slump flat. If it is too stiff to place, add a little water. If it is runny, you have gone too far; the fix is a little more of the dry materials in the correct ratio, never more water.

6. Place it quickly. Mix only what you can place in roughly the next half hour to an hour, and sooner in hot sun. Concrete that has started to stiffen should not be "revived" with more water.

Hand-mixing concrete, in order 1. Measure by bucket, level full 2. Dry-mix until one even colour 3. Water a little at a time 4. Turn until plastic, not runny 5. Place and compact promptly 6. Cure keep damp, 7 days or more The orange steps are where most weak concrete is made: too much water, too little turning
The six steps of hand mixing and placing. None needs special equipment, but skipping the dry-mix or adding water to make shovelling easier undoes the cement you paid for.

Placing and Compacting: Getting the Air Out

Freshly placed concrete is full of trapped air. Left in, those pockets become honeycombing, the rough, stony voids you see on the sides of poorly built bases. On small jobs compaction is done by hand: rodding the concrete with a steel bar or a length of timber, tamping the surface with a straight board, and tapping the sides of the formwork with a hammer until the surface shows a thin film of paste and bubbles stop rising.

Place concrete close to its final position rather than dragging it across the slab, which separates stones from paste; a wheelbarrow tipped straight into the formwork beats a chain of shovels. On deeper bases, pour and compact in layers.

For animal house floors, think about drainage before you pour. A slight fall towards a drain channel stops urine and wash water pooling, which matters for hoof health and for hygiene. Our zero-grazing unit guide covers floor layout for dairy cows. Finish floors that animals walk on with a wooden float or a broom rather than a steel trowel, because a glass-smooth floor becomes slippery when wet. Brick and plastering trowels are on the price list at the time of writing for edges and patches.

Curing in the Short Rains: Damp Is Good, Rain on Fresh Concrete Is Not

Concrete does not dry hard. It hardens because cement reacts chemically with water, a reaction that continues for weeks while moisture is present. If the surface dries out in the first days, the reaction stops near the surface, leaving a weak, dusty skin that wears away under hooves and wheelbarrows. Curing simply means keeping the concrete damp so the reaction can continue.

The common guidance for ordinary cement is to keep concrete continuously moist for at least seven days. Cover it with polythene sheet, wet sacks or a layer of damp sand, and wet it down morning and evening if it is in sun. Shade the slab if you can on hot afternoons.

The short rains help and hurt. Humid, overcast weather makes curing easier, but heavy rain falling on concrete that has not yet set washes cement paste off the surface and pits it. Watch the sky before a pour, start early in the day, and have polythene sheeting and something to weigh it down on site before the first bucket is mixed. Once the concrete has set firm, usually after some hours, rain is no longer a threat to the surface and becomes free curing water.

Keep traffic off for the first days, and keep heavy loads off for longer. A tank base should be well cured before a full tank is placed on it; our guide to tank stands and gravity flow explains how heavy a full tank really is and why foundations are where stands fail.

Hand Mixing or a Mixer?

Hand mixing suits small, spread-out jobs: a trough base, a post footing, a floor patch. The limit is labour: as the team tires, the turning gets shorter and the water goes up.

A hired drum mixer makes sense for one large continuous pour, such as a full animal house floor or a big tank base, where a joint halfway through would be a weakness. It mixes more consistently with less effort, but still needs the same discipline about measuring and water. A mixer that is fed by shovel and topped up with water by eye makes bad concrete faster.

A practical rule many farm builders use: if the job can be done comfortably in a few batches by a small team in a morning, mix by hand on a good platform. If it needs a continuous pour bigger than the team can mix and place without rushing, hire a mixer or split the job at sensible joints planned in advance.

Pre-Pour Checklist

  • Mix chosen for the job, and an engineer consulted for anything structural or heavily loaded.
  • Area measured and squared; bags, sand and ballast calculated, plus a spare bag.
  • Cement stored dry, off the floor, and used in date order; lumpy cement left out.
  • Clean sand and ballast, free of soil, roots and rubbish.
  • Clean mixing platform, standard buckets or gauge box, shovels, a tamping board and floats on site.
  • Formwork firm, level and oiled or lined; ground below compacted and dampened.
  • Clean water to hand; polythene sheeting and weights ready for rain and curing.
  • Gloves, boots and eye protection for the team, since wet cement is alkaline and burns skin with long contact. Our workshop safety and PPE guide covers the basics.

For the tools that make a pour go smoothly, from shovels and trowels to mason hammers, concrete chisels and tapes, see the workshop and industrial tools range or the full price list, and talk to any Fuga branch or WhatsApp 0716 961 018 before you start.

Key Takeaways

  • Use 1 : 2 : 4 (cement : sand : ballast) for general farm floors and bases, 1 : 1.5 : 3 for tank bases and heavily loaded or reinforced work, and 1 : 3 : 6 only for blinding.
  • Measure every material with a level-full bucket or gauge box, never by shovelfuls.
  • Estimate bags from the wet volume times about 1.54, divided by the total parts in the mix; a 4 m by 3 m slab 100 mm thick needs about 8 bags of cement at 1 : 2 : 4.
  • Dry-mix until the colour is even, then add water a little at a time; too much water is the main cause of weak, dusty concrete.
  • Compact by rodding and tamping to remove trapped air, and place concrete close to its final position.
  • Keep concrete damp for at least seven days, and cover fresh concrete before heavy rain in the short rains season.

Frequently Asked Questions

What is the best concrete ratio for a cowshed or goat house floor?

A 1 : 2 : 4 mix (cement : sand : ballast by volume) is the common choice for animal house floors on Kenyan farms. Lay it with a slight fall to a drain and finish it with a wooden float or broom so it is not slippery when wet.

How many bags of cement do I need for one cubic metre of concrete?

As a worked estimate, one cubic metre of 1 : 2 : 4 concrete needs about 6.3 to 6.5 bags of 50 kg cement, based on multiplying the wet volume by about 1.54 for dry materials. A richer 1 : 1.5 : 3 mix needs more. Add a spare bag, and about 10 percent more cement if mixing by hand.

How much water should I add to concrete?

Add water gradually until the mix is plastic and holds its shape when squeezed, without water running out. There is no fixed number of buckets because sand and ballast arrive with different moisture. If the mix becomes runny, add more dry material in the correct ratio rather than leaving it wet.

Can I pour concrete when it is raining?

Light drizzle is manageable if you cover the work, but heavy rain on concrete that has not yet set washes away cement paste and pits the surface. Pour early in the day, watch the weather and keep polythene sheeting ready. Once the concrete has set, rain helps curing.

How long before I can put a water tank on a new concrete base?

Concrete keeps gaining strength for weeks, so keep it damp for at least seven days and avoid full loads early. For a large tank, ask a qualified engineer or the tank supplier how long to wait for the base you have built.